Projects

Abstractions become quantities when you build the thing on paper. Each project below is modelled bottom-up — quantities, materials, processes, labour, capital and returns — and each produced a bottleneck ranking that contradicts the consensus one.

A gigawatt data centre

Modelled bottom-up from the Epoch AI cost study: 1 GW of IT capacity, PUE 1.14, roughly 500,000 Blackwell-class accelerators, 71% utilisation.

Two valid cost lenses

The source plan and the supplied benchmark use different hardware, site and scope assumptions. Read the range as a scenario envelope, not a contradiction.

Project Gigawatt plan$38bn
Servers $21.2bn · facility $11.4bn · network $4.9bn, rounded
Gas-powered benchmark$60bn
IT hardware $41bn · infrastructure $19bn. GPU alone: $30bn.

Shared conclusion: compute owns the capital bill; power equipment owns the schedule.

Where the $38 billion goes

Servers are 56% of upfront capital and 60% of lifetime cost. Anyone analysing this as a real estate project is analysing the wrong asset — it is a compute purchase wearing a construction project's clothing.

Facility capex decomposition

Electrical infrastructure is the largest single category in the building — larger than cooling and shell combined. The building itself is only 10–15%.

The critical path is procurement, not construction

A heavy-duty gas turbine ordered today delivers in 2031. Large power transformers run 128 weeks. The shell takes 18–36 months. The equipment takes longer than the building, which means orders must be placed before the land is bought.

Programme schedule, conventional procurement

Accelerated paths reach 30–40 months using behind-the-meter generation to bypass the interconnection queue, pre-reserved turbine slots, modular electrical skids and phased energisation in 100 MW blocks.

Bill of materials

Compute and electrical plant

Raw materials and land

One facility consumes roughly 4% of the world's annual high-bandwidth memory output and 0.2% of global copper mine production.

Three ways to power it

Serving 1 GW of IT at PUE 1.14 requires roughly 1.15 GW of firm, continuous supply and about 7.1 TWh a year. Firmness is the requirement that eliminates most options immediately.

The strategic conclusion

Energy source changes annual cost by a few hundred million dollars on an $8.5bn annual total. It changes the schedule by years — and schedule determines whether the asset exists at all. Choose for speed to power, not for levelised cost.

Solar sized for genuine round-the-clock firmness needs roughly fourfold overbuild plus overnight storage, occupying on the order of 100 km² — about ninety times the campus it serves. Its realistic role is a fuel-cost supplement, not a sole source.

Most real projects land on a hybrid: grid where available, behind-the-meter gas for firmness and speed, solar for fuel cost, and a long-dated nuclear PPA for the 2030s. Pure-play strategies are for press releases.

Does it pay?

Break-even price per GPU-hour at a 12% hurdle, across four energy scenarios and three depreciation assumptions. Read down, not across.

Break-even price per GPU-hour

The depreciation axis spans $1.66; the energy axis spans $0.19. Depreciation swings the answer 8.7 times harder than the choice between gas, solar and nuclear.

Break-even by utilisation rate

At 50% utilisation even the seven-year case needs $3.75, above the contract floor. Utilisation is the second most powerful variable, and the one that breaks first if demand softens.

Market reference, 1 September 2026

The verdict on each case

Base case at grid power, five-year life and $4.00 per GPU-hour: NPV $13.1bn, project IRR 20.2%, payback in year five, $124bn of ten-year revenue against $64bn of capital deployed including one server replacement cycle.

Labour, capital structure and who is actually building

Workforce

$38 billion of capital creates roughly 300 permanent jobs. Derived from the $40m annual labour line. Meta's Hyperion reports 7,500 peak construction jobs and about 1,000 permanent for 5 GW — the same ratio.

Capital structure, typical 2026 shapes

A representative neocloud carries five-year loans against three-year customer contracts and fifteen-year leases. Borrowing long against depreciating collateral with short revenue is the oldest failure mode in project finance.

Gigawatt-scale projects under construction or operational

Nineteen of eighty-four tracked facilities carry 1 GW or more, together 27.9 GW — roughly 65% of tracked capacity in under a quarter of the sites. Texas alone hosts 15 facilities and 14.8 GW. Announced capacity is not delivered capacity: only about a third of announced 2026 US capacity was under active construction.

Risk register and decision gates

Risk register

Go / no-go gates

Gates one and two must clear before land is purchased. The conventional sequence — buy land, design, then procure — is how projects end up as powered shells with no power. In this market, procurement leads development.

What this exercise reveals about the thesis

Sources

Ten million humanoids

A fundamentally different engineering problem. Modelled bottom-up from a mid-range commercial humanoid: 45 actuators, 2.0 kWh battery, 350 W average draw, 16 hours a day.

Layer 1Robot hardware450m actuators
250m precision reducers
Layer 3Edge intelligence10–30 Hz action loop
~1.3 GW distributed compute
Layer 4Fleet data200 Tbps raw ceiling
selective upload required
Layer 5Training + simulation3–5 GW central compute
synthetic + real data
Layer 6Deployment3–5m docks
~5 GW peak charging

The five layers a working fleet requires

The bottleneck is mechanical, not computational

Fleet demand measured against today's entire world output. One number dominates: the precision reducer industry must grow roughly fiftyfold. Batteries, sensors and copper — the inputs people worry about — are rounding errors at fleet scale.

Component demand for 10 million units

A strain-wave reducer uses a thin-walled steel cup that deforms elastically millions of cycles without fatigue failure. The constraint is metallurgy, heat treatment and grinding capacity — none of which can be bought quickly.

Where the cost sits

Bill of materials by platform

A twentyfold spread tells you these are not competing in the same market. Chinese supply-chain BOM was around $46,000 in 2025, projected to fall at roughly 11% CAGR to about $16,000 at one million units a year around 2034.

The battery is the worst constraint and the least important one

No commercial humanoid runs a full eight-hour shift. Cells sit at 280–300 Wh/kg, close to the practical lithium-ion ceiling. Yet fleet demand is 20 GWh — 1.1% of world output. Severe per robot, negligible per fleet.

Platform battery specifications

The physics trap: adding a kilowatt-hour adds mass, which raises hip and knee torque demand, which eats the runtime the extra capacity was meant to buy. Duty cycles also demand 5C–15C discharge for grasping and stumble recovery, in a package with almost no airflow.

Edge inference, measured

The central technical tension: the models good enough to be commercially useful do not yet run fast enough on hardware small enough to carry. Jetson Thor falls below the frame rate of most cameras. Every deployment today is a compromise between capability and latency.

The data problem solves itself at scale

Today there are roughly 500,000 hours of high-quality robot interaction data in existence, against an estimated 1–10 billion needed. A ten-million-robot fleet generates 58.4 billion hours a year — reproducing the entire existing global corpus every 4.5 minutes.

What this implies strategically

The data gap is real today and effectively disappears above roughly one million deployed units. That creates severe winner-take-most dynamics: whoever reaches fleet scale first acquires an asset a later entrant cannot replicate with capital. It explains behaviour that otherwise looks irrational — deploying at negative margin to get past the threshold.

The counter-argument is serious. Carnegie Mellon and Stanford independently found in 2026 that policies trained on 40% synthetic data matched policies trained on 100% real demonstrations. If that holds, real data is a threshold asset, not a scaling asset — you need enough to seed the simulator, and the race has a finish line closer than the raw hour counts imply.

Energy, capital and the timeline

Fleet energy and communications

Ten million humanoids consume less electricity than three AI data centres. But 200 Tbps of continuous uplink is not buildable — which forces robots to curate their own data on board and upload only novel, failed or corrected episodes.

Capital and economic output

At $10/hour the fleet pays back its hardware in about a year. The arithmetic is compelling; the productivity assumption behind it is a hypothesis. Unitree ships more humanoids than anyone and its Q1 2026 net profit fell 52%.

Why this is 2034, not the near future

Reaching 10 million cumulative units requires doubling production every year for nine consecutive years from a 2026 base of roughly 20,000. No hardware industry has ever sustained that — and none faced a component whose supply chain must grow fiftyfold.

Bottleneck ranking

Deployment infrastructure — the layer everyone omits

A robot that works is not a robot that is deployed. Every reducer, actuator and bearing in the fleet is a wear component with a finite duty life.

Ten million robots with 45 actuators each implies a maintenance economy that does not currently exist and for which no training pipeline has been built. The humanoid industry will create far more maintenance jobs than platform-manufacturing jobs — a point almost entirely absent from a public debate focused on displacement.

The security dimension carries unusual force here. An agent with credentials that can only write to a database is a data breach risk. An agent with credentials that can lift 25 kg is a physical safety risk. Machine identity, per-action authorisation and delegation-chain tracking move from a compliance concern to a life-safety one — and regulation should be expected here before it arrives for software agents.

Companies positioned in the humanoid supply chain

The volume thesis on actuator components is the strongest picks-and-shovels case in the AI complex. The margin thesis is under direct attack: Green Harmonic prices 30–50% below the Japanese incumbents, is already inside Tesla's supply chain, and targets 60% share. You can be completely right that 250 million reducers get built and still lose money owning the incumbent.

What would make this analysis wrong

Sources